DumpsBase offers the most up-to-date AACE CCP dumps (V9.02) that emulate the latest AACE Certified Cost Professional (CCP) exam content, ensuring that your practice is always aligned with what the AACE CCP certification demands, giving you confidence and peace of mind. The AACE CCP dumps from DumpsBase are structured to break down even the most complicated subjects in the Certified Cost Professional (CCP) certification program. The questions and answers in the dumps are presented in an approachable style, allowing you to gauge your preparation readiness and strengthen your weaker domains. This helps in developing a strategic study approach that increases your odds of passing the AACE CCP exam on the first attempt.

Below are the CCP free dumps (Part 1, Q1-Q40) for reading to check the CCP dumps (V9.02) first:

1. The four steps to writing are:

2. A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

In an exit interview, an employee comments that the reason he is leaving the organization is lack of teamwork and cohesion among his co-workers.

Which need of Maslow's hierarchy of needs is unmet?

3. A systematic coding structure for organizing and managing scope, assets, cost, resources, work and schedule activity information is a______________.

4. The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

If steel costs $1800/ton at the end of Year 3, what is the price of steel at the end of Year 4?

5. AACE International defines _____________as a technique of economic evaluation that sums over a given study period, the costs of initial investment, replacements, operations, and maintenance/repair; expressed in either present or annual value terms.

6. The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

9,375 hours have been expended to date. Planned completion at this time is 75%. The project is determined to be 66% complete.

What is the current cost performance index (CPI)?

7. A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

Fred Fiedler's contingency model suggests that:

8. _____________is defined as the budget for the cost (work) account times the percent complete for that account.

9. A contract clause that provides the owner with the right to terminate the contract irrespective of the general contractor's liability is:

10. Listening to what is being said by all members of a group or audience and then summarizing or interpreting is called______________.

11. Any combination of unique letters, numbers, or blanks, which describes and identifies any activity or task shown on the schedule, is:

12. A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Which statement best describes the type of information available for a design phase estimate?

13. A work breakdown structure (WBS) is developed because:

14. The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen., using the drop down menu, to reference during your response/choice of responses.

What is the range of unit costs?

15. What is a basic element of work or a task that must be performed over a given period of time in order to complete a project called?

16. A concrete slab measuring 10 feet wide by 13.5 feet long by 6 inches deep is to be installed.

How many cubic yards of concrete will be required?

17. Two of the most important things to know when planning a speech or lecture are the ______________and______________ of your audience.

18. The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

At the end of 30 months, the final price for the piece of equipment will be:

19. The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

9,375 hours have been expended to date. Planned completion at this time is 75%. The project is determined to be 66% complete.

What is the current schedule performance index (SPI)?

20. Some of the principles of good communication are:

21. The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

At the end of Year 3, steel prices will have increased by what percentage over today's price? (round to 1 decimal)

22. What is executed in connection with a contract and secures the performance and fulfillment of all the undertakings, covenants, terms, conditions and agreements contained in the contract?

23. The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

9,375 hours have been expended to date. Planned completion at this time is 75%. The project is determined to be 66% complete.

Based on current trends, how many hours will be expended at project completion?

24. The latest allowable end time minus the earliest allowable end time on a schedule activity is referred to as:

25. A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

Which of the following percent complete measurement techniques is best suited for long-term non-production accounts (such as overhead accounts)?

26. The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen., using the drop down menu, to reference during your response/choice of responses.

Calculate the weighted average unit cost.

27. A schedule's late dates are calculated during the:

28. The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Calculate the mean unit cost.

29. A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Why is a +/- notation necessary when developing an estimate?

30. In a fixed price contract the:

31. An effort by a prime contractor to reduce the price quoted by a vendor, by providing the bid price to other vendors in an attempt to get the other vendors to underbid the original price quoted is referred to as:

32. The purpose of a communication must be understood by ____________ if the message is to be clear to the

33. A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Select the statement that best describes the method to estimate the cost of the new rides:

34. The written word is often more useful than the spoken. Guidelines for writing include:

35. The goal of listening is to:

36. If a project is said to be on a "fast track program/' the fast track method is:

37. ____________ is the application of total resources ($-workers-supports) and activity durations of the logic diagram.

38. A bond that guarantees the bidder will enter into a contract on the basis of his/her bid is referred to as:

39. The process of stating goals and determining the most effective way of reaching them is the definition for:

40. The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

10,278 hours have been expended to date. The CPI at this point in time is 0.93. SPI is 1.03.

How many hours have been earned?


 

 