DumpsBase updated the CPIM-8.0 dumps to V10.02 with 570 practice questions and answers, always aligned with the most current exam syllabus. Our team of certified experts conducts regular reviews and updates to incorporate the latest changes, ensuring you have access to the most updated CPIM-8.0 exam questions and answers on the market. Trust, our updated CPIM-8.0 exam dumps eliminate guesswork, providing a comprehensive toolkit for triumph in the Certified in Planning and Inventory Management (CPIM) exam. Skip outdated or questionable sources —DumpsBase equips you with everything needed for a confident, efficient path to CPIM certification success. Before downloading the most updated dumps, you can check our free demos first. Today, we will share our free dumps first.

Read our CPIM-8.0 free dumps (Part 1, Q1-Q40) of V10.02 first:

1. Which of the following actions will result In lower inventory levels?

2. How would a master production schedule (MPS) be used In an assemble-to-order (ATO) manufacturing environment?

3. An effective approach to projecting requirements for materials with long lead times Includes which of the following options?

4. A manufacturer has a forecasted annual demand of 1,000,000 units for a new product. They have to choose 1 of 4 new pieces of equipment to produce this product. Assume that revenue will be $10 per unit for all 4 options.

Which machine will maximize their profit if the manufacturer anticipates market demand will be steady for 3 years and there is no residual value for any of the equipment choices?

MachineFixed CostVariable Cost per UnitAnnual Capacity

AS100.000$6 00800,000 units

B$200,000$5 501.000,000 units

C$250,000$5 001,200,000 units

D$1 000.000$4 501 400.000 units

5. A logistics manager Is faced with delivering an order via rail or truck. Shipping via rail costs S300 and takes 14 days. Shipping via truck costs $600 and takes 3 days.

If the holding cost is $40 per day, what is the cost to deliver the order?

6. In a lean environment, the batch-size decision for planning "A" items would be done by:

7. A plant uses a level production strategy due to the high costs of hiring and letting go of skilled employees. The constrained resource is due to be upgraded in the fourth month of the planning horizon, and that will reduce capacity for that month by 17%.

Which of the following actions would be appropriate in this situation to maintain current levels of customer service and gross margin?

8. Which of the following production activity control (PAC) techniques focuses on optimizing output?

9. Which of the following actions hinders the transition from a push system to a pull system?

10. Which of the following items does the master scheduler have the authority to change in the master scheduling process?

11. Labor3 people

Work hours10 hours per day

Days4 days per week

Meetings with work area employees1/2 hour per day

Work area efficiency85%

Given the information above, what is the weekly theoretical capacity of this work area in hours?

12. Which of the following product design approaches are likely to reduce time to market for a global supply chain?

13. The horizon for forecasts that are input to the sales and operations planning (S&OP) process should be long enough that:

14. A newer automotive supplier has not fully developed its information technology (IT) systems. The supplier has Just received a contract from a large automotive manufacturer which requires the supplier to use electronic data interchange (EDI) transactions for receiving orders, sending advance ship notices (ASNs), and receiving invoice payments.

What strategy can the supplier adopt to immediately meet the EDI requirements?

15. Which of the following statements best characterizes enterprise resources planning (ERP) systems?

16. The question below is based on the following information:

Beginning inventory = 43Week 1Week 2Week 3

Forecast202020

Customer orders221710

Projected on-hand

Master production schedule (MPS)80

Available-to-promise (ATP)

What is the largest customer order that could be accepted for delivery at the end of week 3 without making changes to the master production schedule (MPS)?

17. For a process that is outside its upper control limit (UCL), which of the following techniques would best be used to return the process under control?

18. If the total part failure rate of a machine is 0.00055 failures per hour, what would be the mean time between failures (MTBF) in hours?

19. If fixed costs are §200,000 and 20,000 units are produced, a unit's fixed cost is §10.

This is an example of:

20. An advantage of applying ABC classification to a firm's replenishment items is that:

21. Which of the following statements is an assumption on which the economic order quantity (EOQ) model is based?

22. One advantage of adopting a supply network perspective Is that it:

23. Based on the values reported in the table below, what is the inventory turnover?

24. Which of the following methods places a replenishment order when the quantity on hand falls below a predetermined level?

25. Which of the following attributes describes a company with a global strategy?

26. When the discrete available-to-promise (ATP) method is used, the master production receipt quantity is committed to:

27. An example of an assignable cause of variation in process performance is:

28. Which of the following circumstances would cause a move from acceptance sampling to 100% inspection?

29. The primary outcome of frequent replenishments in a distribution requirements planning (DRP) system is that:

30. If all other factors remain the same, when finished goods inventory investment is increased, service levels typically will:

31. A company assembles kits of hand tools after receipt of the order from distributors and uses two-level master scheduling.

The appropriate levels of detail for the forecasts that are input to master scheduling would be total number of kits and:

32. A company has a demand for 30 units of A, 40 units of B, and 50 units of C. These products are scheduled to run daily in batches of 10 as follows: ABC, ABC, ABC, CBC.

What is this scheduling technique called?

33. Which of the following activities is an example of collaboration between suppliers and operations which would give more lead time visibility?

34. Fishbone diagrams would help a service organization determine:

35. The question below is based on the following standard and actual data of a production order

Which of the following statements about variances is true?

36. Check sheets can be used to:

37. In which of the following phases of the product life cycle is product price most effective in influencing demand?

38. A company that uses concurrent engineering is likely to experience which of the following outcomes in the first period of a product's life cycle?

39. Management should support investments in new process technologies that:

40. The master schedule is an Important tool in the sales and operations planning (S&OP) process because it:


 

CSCP Dumps Updated - Choose DumpsBase CSCP Exam Dumps (V11.02) to Complete the APICS Certified Supply Chain Professional Certification Exam

Add a Comment

Your email address will not be published. Required fields are marked *