Getting the Latest RCDD Study Guide to Make Preparation: The RCDDv15 Dumps (V8.02) with Free Dumps (Part 1, Q1-Q40) Online

We know that the BICSI Registered Communications Distribution Designer (RCDD) has been updated to version 15; you need to take the RCDDv15 and achieve success. DumpsBase is specifically designed for the latest RCDD study guide, RCDDv15 dumps (V8.02), to help you accomplish your BICSI Registered Communications Distribution Designer – RCDD v15 exam on the first attempt. RCDDv15 dumps (V8.02) contain 320 practice questions and answers. All the questions provided are modeled closely after those found in the actual RCDD exam. This means that when you practice with DumpsBase RCDDv15 exam dumps, you’re essentially experiencing the exam environment in advance. We have free dumps to help you check the quality. The RCDDv15 free dumps (Part 1, Q1-Q40) are below for testing online.

Start reading our RCDDv15 free dumps (Part 1, Q1-Q40) below:

1. A municipal agency manages a city's water and wastewater infrastructure. A regulation requires the replacement of sewer lines throughout the city at a cost of US$2 billion over 30 years

The city has been managing this program with various program teams, and has a project controls office In place to track protects separate from the program management team A program manager is hired to standardize all deliverables from component projects under the program.

What should the program manager do next?

2. What is the derating factor for a 24 AWG (0.51 mm) stranded cords?

3. Which two of the following apply during a project’s close out process? (Choose two.)

4. Which type of protection for electrical power stations provide isolation against a rise in potential of station ground and also provide drainage protection against longitudinally-induced voltages?

5. Company A recently signed a contract with a strategic business partner, Company B, to jointly roll out a new technology Company B is excited about the joint marketing opportunity Company A's component Quality Assurance team has expressed concerns to you the program manager, Ural the product is being rolled out prematurely and has identified potential issues with backend support systems. QA, however, assures you that a manual work around is possible, but not ideal Company B requests an enhancement to the new product. In a meeting with Company B, you determine that additional funding will be required and resources allocated and scheduled

What is your MOST appropriate next step?

6. Several issues are identified on one component project in a program During a meeting with that component's project manager, the program manager offers several suggested resolutions Two weeks later, they meet again to review progress. The project manager had reviewed the issues and suggested resolutions, but delayed a decision. This two-week delay in taking action caused delays in the project schedule

What should the program manager do?

7. When planning a telecommunication termination area, what is the estimated space needed to terminate 144 strands of optical fiber?

8. DRAG DROP

Identify the fibers below as either single mode (SM) or multi-mode (MM) by dragging the appropriate term into each oval.

9. Component project managers create project management plans for all component projects in a program. The program manager notices that some project managers prefer one status report template while others prefer another

How should the program manager decide which template is appropriate?

10. Which two of the following items MUST be included in a detailed SoW? (Select two options.)

11. Which two of the following are means in which radiated interference primarily enters electronic devices? (Select two options.)

12. A regional finance program is impacted by a new currency regulation issued by a country in the region. The new regulation requires changes to the financial statements of that country's branches by the end of the fiscal year Failing to comply with the regulation may result in fines and/or closure of the branches. A branch general manager immediately meets with the program manager to select and secure a local fiscal expert to support the regulation as these types of resources are in high demand. There is a high risk that the changes will not be completed on time if the resource is not secured

What should the program manager do to address the risk?

13. One of the constituent project managers asks a new program manager to obtain approval for an additional key project requirement.

A tolerance range is set, if the tolerance range is too narrow on a program what effect will multiple minor changes have on the program?

14. As a project manager, what should the FINAL task be at of the end of each project?

15. A program manager initiates a new global program to create a higher level of protection for a company's intellectual property. The company exhibits a relaxed culture and environment and is intolerant of processes to the point of being considered process-adverse However, the company's culture is tolerant of long-term program activities, and provided there is continuous progress on improving the protection of its intellectual property Expectations for rapid progress are low

What should the program manager do next?

16. A software company's program manager is conducting closing procedures for a program. At the last steering committee meeting, realized benefits were presented to the program governance board.

What should the program manager do next?

17. An organization is embarking on a new program aligned with its strategic objectives. The new program has a High level of risk due to the rapidly changing technical landscape in which the organization operates. The organization has mature program management capabilities, as measured by its resources, intellectual assets, and management processes.

Given the organization's history of delivering successful programs, what should the program manager do as part of the planning process?

18. An ICT distribution designer is reviewing a client's site information (spaces and pathways) to determine network technology and equipment selection. This is referred to as a___________design process

19. A natural disaster shuts down operations for two days. The program has a major milestone that includes a timed payment of USS1 million.

Since the shutdown was not anticipated, what should the program manager do first?

20. A program manager recognizes that a successful resource being used in project A could also be used in project B.

What should the program manager do first to leverage the utilization of this resource?

21. Throughout a multiyear program, component projects are transitioned to the customer. During the project acceptance phase, a potential risk is identified and brought to the program team's attention.

What should be done with the identified potential risk?

22. A project's installation start involves a Kickoff Meeting and the General Contractor's Coordination Meeting.

As part of the designer's responsibilities, which two of the following ate key elements of the Kick-off Meeting? (Select two options.)

23. The new performance financial system is delivered lo all business entities on time following a one-year implementation program After six months of utilization the global finance department one of the main beneficiaries of the program, determines that quality and level of granularity of the financial data is not sufficient for them to analyze the key performance indicators (KPIs) defined Additionally, the global finance department is missing the analytical tools required to understand the causes of discrepancies

To address these shortcomings the global finance department submits a request for a follow-up initiative through the process defined by which of the following documents?

24. The customer of a three-year program does not want to receive any intermediate details on the program. The program appears to be in trouble and the customer is concerned about a

new system's cost. The program manager has provided monthly performance reports throughout the program's lite cycle.

Which of the following would the customer be interested in reviewing?

25. A company's marketing department Tails an internal compliance audit. To comply with the auditor's remediation plan the legal department mandates that a content management system (CMS) be implemented After initiating the program for CMS implementation the program manager discovers that the marketing department has already preselected which CMS technology will be implemented.

What should the program manager do to ensure the success of the program?

26. An ICT distribution designer is preparing a price quote for a building design with multiple floors originally sized at 40.000 ft (3716 m2). While the designer is preparing the quote, the structural engineer indicates the building has been increased in size to accommodate an additional 40,000 ft2 (3716 m3) per floor. The designer's recommendation to the engineer will be to increase the slot area by_____for each additional 40,000 ft3 (3716 m2)

27. Which stakeholder of a project team is responsible to provide closeout documentation to the client? Architect

28. CORRECT TEXT

A program manager joins a team during its preparation phase.

What should the program manager do lo obtain formal sponsor approval to begin the benefits delivery phase1?

29. A program manager concurrently implements a software program at four client locations.

The client's objective is to maintain quality while shortening the software implementation timeline

What key elements should be included in the benefits register to achieve this goal?

30. A three-year program using vendor contracts, incorporating related projects, and each with specific stakeholders is coming to an end.

What should be completed first to close all appropriate contracts?

31. A program manager is appointed to manage a new program. The organization's leadership has specified a list of benefits (hat the program should deliver and has requested that the program manager determine when incremental benefits can be realized.

What should the program manager do first?

32. A large international manufacturing company is centralizing its IT which is currently spread over 16 countries. The transition means physically regrouping the infrastructure and aligning processes and organizations.

The high-level scope of this transformation encompasses three main areas.

1. The technology area―assessing which technology/tooling should be retained for the target data center

2. The policies and procedure area-aimed at establishing a common set of processes supporting the new way of delivering services

3. The HR area-assuring the new organization best fits the diversity of the countries and functional domains, while offering equivalent compensations for comparable functions

You have selected your team and you are preparing the business case to support 1) the team selections you made and 2) your recommendation to proceed to the program's next phase

Which document should be present m your business case?

33. The project manager of project A develops a communications management plan. The project manager of project B is new and is uncertain how to develop appropriate communications for the company's staff

What should the program manager do to ensure communications on the component projects are consistent?

34. An R&D group director approves a major program's charter although the director has a high level of understanding of the program's scope (hoy are unsure of how the program manager can be successful in delivering the program's commitments

What should the program manager do to align stakeholders with planning and monitoring the program's progress?

35. What is the MAXIMUM recommended length for A in the image below?

36. A program will generate revenue for several years after it ends. The program manager and the operations manager, who are accountable for managing the benefits after program closure, are in disagreement. The operations manager is concerned that information necessary for managing the processes and benefits after program closure will be unavailable. The program manager expresses that managing the benefits after program closure is not within the scope and must be managed through the scope management plan.

What should the program sponsor do?

37. The type of apparatus housed in ERs varies greatly in size, purpose and function.

Which two of the following active equipment is included? (Select two options.)

38. The program manager leads a medical billing system integration program for company A. a health services provider Company A acquires smaller company X. which delivers health services strategically aligned with company A Company X uses a different billing approach than company A. Company A's chief information officer (CIO) seeks counsel on which solution would be the better option moving forward requesting the program manager's assistance.

How should the program manager respond to the ClO's request1?

39. A program manager at a pharmaceutical company plans a new drug development effort. The development is slated to yield three drug variants. The program manager articulates the program scope boundaries.

Which of the following deliverables captures these items?

40. The program manager takes over a poorly performing program After a review of the documentation and interviews with the program sponsor, stakeholders and program constituents, the program manager realizes that the program is not aligned with the corporate/organizational goals. The program manager must realign the constituent protects and components to meet the program's needs

What action should the program manager take to realign the program?


 