300-615 DCIT Is One OF Concentration Exams For CCNP Data Center Certification

Shamiyo 03-31-2020

Before writing Cisco 300-615 Troubleshooting Cisco Data Center Infrastructure (DCIT) exam, you need to know Cisco 300-615 DCIT exam is one of concentration exams for CCNP Data Center certification. Also, you need to choose valid online resource to do the best preparation. However, where can we get the most valid 300-615 exam dumps t prepare for Troubleshooting Cisco Data Center Infrastructure (DCIT)? It is highly encouraged to choose DumpsBase new 300-615 exam dumps to read all real exam questions and accurate exam answers to pass Cisco CCNP Data 300-615 exam in the first try. The professional team collected all 300-615 exam questions and answers based on the exam topics. Each question and answer can help you master the skills and knowledge of 300-615 exam.

CCNP Data Center Certification Has Been Updated To Prove Your Skills With Data Center Solutions

Cisco updated its certification tracks and levels since February 24, 2020, including Cisco CCNP Data Center certification. 

Before February 23, 2020, there were two paths for completing your CCNP Data Center certification:

Path One: Design Path For CCNP Data Center Certification

This path required you answer four exams:

300-175  DCUCI Implementing Cisco Data Center Unified Computing (DCUCI)

300-165  DCII Implementing Cisco Data Center Infrastructure (DCII)

300-170  DCVAI Implementing Cisco Data Center Virtualization and Automation (DCVAI)

300-160  DCID Designing Cisco Data Center Infrastructure (DCID)

Path Two: Troubleshooting Path For CCNP Data Center Certification

Also, this path required you answer four exams:

300-175  DCUCI Implementing Cisco Data Center Unified Computing (DCUCI)

300-165  DCII Implementing Cisco Data Center Infrastructure (DCII)

300-170  DCVAI Implementing Cisco Data Center Virtualization and Automation (DCVAI)

300-180  DCIT Troubleshooting Cisco Data Center Infrastructure (DCIT) 

However, both the two path are not available now any more. All abve 5 exams were retired on February 23, 2020. 

Currently, you need to complete a core exam and a data center concentration exam of your choice.

CCNP Data Center Core Exam

CCNP Data Center Core Exam focuses on your knowledge of data center infrastructure, you are required to complete 350-601 DCCOR Implementing and Operating Cisco Data Center Core Technologies (DCCOR).

CCNP Data Center Concentration Exams

CCNP Data Center Concentration Exams focus on emerging and industry-specific topics. There are 5 exams, you need to choose one of them to complete.

300-610 DCID Designing Cisco Data Center Infrastructure (DCID)

300-615 DCIT Troubleshooting Cisco Data Center Infrastructure (DCIT)

300-620 DCACI Implementing Cisco Application Centric Infrastructure (DCACI)

300-625 DCSAN Configuring Cisco MDS 9000 Series Switches (DCMDS)

300-635 DCAUTO Implementing Automation for Cisco Data Center Solutions (DCAUI)

300-615 DCIT is one of concentration exams, if you are one candidate who are preparing for 300-615 Troubleshooting Cisco Data Center Infrastructure (DCIT) exam, come to DumpsBase to get the most valid 300-615 exam dumps now.

Differences Between 300-180 DCIT And 300-615 DCIT

We can find that 300-615 DCIT exam has the same full name as 300-180 DCIT exam. What are the differences between the two exams? 

First, 300-615 DCIT and 300-180 DCIT Have Different Exam Topics.

300-615 DCIT exam is new one for current CCNP Data Center certification, which tests your knowledge of troubleshooting a data center infrastructure, including Network, Compute platforms, Storage network, Automation, Management and operations.

But, 300-180 DCIT exam has different exam topics, it tests your knowledge of troubleshooting Cisco data center infrastructure including:

● Data network protocols

● Network virtualization and automation

● Application Centric Infrastructure (ACI)

● Storage

● Compute platforms

● Management and operations

Second, 300-615 DCIT exam is also for Cisco Certified Specialist - Data Center Operations certification.

Different from 300-180 DCIT exam, Cisco 300-615 DCIT exam is not only for CCNP Data Center certification, but also for Cisco Certified Specialist - Data Center Operations certification.

Check 300-615 DCIT Free Dumps To Find DumpsBase 300-615 Dumps Is Valid

A vPC Type-1 inconsistency between two vPC peers in a VXLAN EVPN setup is discovered.

Which two actions need to be attempted to resolve the issue? (Choose two.)

A. Configure the NVE interfaces to be Up on both switches.

B. Set a different distributed gateway virtual MAC address.

C. Set a different secondary IP addresses on NVE source-interface.

D. Configure the same VNI to multicast group maping.

E. Set a different primary IP addresses on NVE source-interface.

Answer: AD

A mission-critical server is connected to site A. Connectivity to this server is lost from site B because the MAC route is missing in the OTV VDC of the Nexus 7000 in site B due to MAC aging.

Which action allows the flooding of the unknown unicast MAC on the Nexus 7000 in the OTV VDC?

A. Use route-map to advertise this MAC statically and redistribute with ISIS.

B. Unknown unicast flooding is not allowed.

C. Use the otv flood mac <> command to selectively flood traffic for a given MAC.

D. Use the otv isis bfd <> command to configure BFD protocol.

Answer: B

The Cisco Nexus switch is connected to a peer switch that is not running Cisco NX-OS. The switches are connected using port channel and are experiencing packet loss.

Which action should be performed on the Cisco Nexus switch ports to resolve this issue?

A. Turn on lacp suspend-individual.

B. Turn on lacp graceful-convergence.

C. Turn off lacp graceful-convergence.

D. Turn off lacp suspend-individual.

Answer: C

An engineer is troubleshooting a fabric discovery failure.

Which two requirements must an engineer verify about switch connectivity to solve the problem? (Choose two.)

A. A Cisco APIC must be attached to a spine node only.

B. A Cisco APIC must be attached to leaf nodes.

C. Spine nodes must connect to other spine nodes.

D. A Cisco APIC must be dual-attached to two separate spine nodes.

E. Leaf nodes must connect to spine nodes only.

Answer: BE

A customer configures HSRP between two data centers that are interconnected with OTV. The configuration succeeds, but traffic between two ESXi virtual hosts on the same site is routed suboptimally through the OTV overlay.

Which two actions optimize the traffic? (Choose two.)

A. Disable first-hop redundancy.

B. Filter HSRP traffic by using a Layer 3 VACL on the OTV edge devices.

C. Filter HSRP by using a Layer 2 MAC-list on the ESXi vSwitch.

D. Filter HSRP traffic by using a Layer 3 VACL on the ESXi vSwitch.

E. Filter HSRP by using a Layer 2 MAC-list on the OTV edge devices.

Answer: AB

An engineer removes a VMM domain from an endpoint group called EPG-1, but the distributed port group fails to be deleted.

Which action must be taken to resolve the issue?

A. Remove the port group manually.

B. Migrate all virtual machines in the EPG-1 to different hypervisors.

C. Remove the remaining EPGs from the VMM domain.

D. Migrate all virtual machines in the EPG-1 to different port groups.

Answer: C

An engineer is troubleshooting a packet flow from an access leaf to spine.

Which EVPN routes are expected on this connection?

A. EVPN Type 1-5

B. EVPN Type 0,9,15

C. EVPN Type 9-15

D. EVPN Type 0,16

Answer: A